Sanitary sewer replacement & street repair at an industrial campus — St. Louis, MO
City of St. Louis · 2023
Project summary
On an active industrial campus in the City of St. Louis, a section of 15" sanitary main had failed. Kuesel replaced it with 15" SDR 26 pipe and repaired a 6" lateral.
Crews then restored the street with 10" of concrete, all under traffic control.
| Location | St. Louis, MO |
|---|---|
| Market | Industrial |
| Scope | 15" sanitary replacement, lateral repair, concrete street repair, traffic control |
Challenge → approach
The sewer ran under a street that both plant and public traffic depended on. Kuesel worked under traffic control so traffic kept moving, replaced the failed main and lateral, and closed the cut with full-depth concrete.
Scope delivered
- Replaced existing 15" sanitary sewer with 15" SDR 26
- Repaired 6" lateral
- 10" concrete street repair
- Traffic control
Key quantities
- 15" SDR 26 sanitary main
- 6" lateral repair
- 10" concrete street repair
Services used
Invite Kuesel to bidWhat each service covered
Site Demolition
Structural and site-specific demolition with full waste management and recycling.
Water & Sewer Infrastructure
Underground utility construction — water lines, sanitary sewer, storm sewer, and manholes for commercial and industrial site work.
Other industrial projects
Clarksville, TN
Full scope heavy civil — mass earthmoving, site utilities, stabilization, paving
View project →O'Fallon, MO
Curb removal, yard grading, crushed limestone surface, concrete approach, storm and erosion control
View project →