Site conditionsCentral Missouri: university and infrastructure
Work in Columbia has included both university campus ground and utilities along a busy interstate. Relocations next to highway work start with hydro excavation of existing lines, and campus stabilization is coordinated with the GC and testing agency.
Project proofKuesel projects in and near Columbia
Columbia: Sanitary and water relocations for an interstate widening in Columbia: utilities hydro-excavated first, 745 LF of 8" sanitary relocated, and about 400 LF of water main moved with a live tie-in.
In Columbia, MO
Interstate Utility Relocations
Sanitary and water relocations for an interstate widening in Columbia: utilities hydro-excavated first, 745 LF of 8" sanitary relocated, and about 400 LF of water main moved with a live tie-in.
View project →
In Columbia, MO
University Track & Soccer Upgrade
Kuesel performed union-labor soil stabilization to a 12-inch depth for the university track and soccer upgrade. Compaction was by others.