Clarksville tire plant Phase II expansion (2.2M SF) – sitework, stabilization & utilities — Clarksville, TN
Montgomery County

Project summary
Kuesel performed full-scope heavy civil work on a tire plant expansion in Clarksville, Tennessee.
The 1.4 million square foot expansion required 2.1 million yards of earth to be moved. The work stayed on schedule through three winters.
Kuesel self-performed the site utilities and soil stabilization, including lime treatment of the industrial building pad.
This is Kuesel's largest project to date, and Kuesel has worked multiple phases at the Clarksville plant in Montgomery County. Phase II added 2.2 million SF of new production and support facilities on the campus, plus additions to the existing plant, rail spur additions and deep equipment pits. It doubled the plant's passenger and light-truck tire capacity and added truck and bus tire production, which started in late 2024.
| Location | Clarksville, TN |
|---|---|
| Market | Industrial |
| Scope | Full scope heavy civil — mass earthmoving, site utilities, stabilization, paving |
| Key facts | 1.4M sq ft plant expansion · 2.1 million yards moved · On schedule through three winters |
Challenge → approach
Phase II combined a huge earthwork balance with deep, precise excavation: tunnels and mixing, cooling-water and carbon unloading pits cut inside a building pad that also had to be lime-stabilized at three different depths and rates. Kuesel located existing utilities by hydro excavation and ran the work under a full SWPPP.
Phase II (2024)
On Phase II, Kuesel cleared about 80 acres and moved about 475,000 CY of mass cut and fill, plus more than 190,000 CY of structural and deep pit excavation for tunnels and mixing, cooling-water and carbon unloading pits.
Crews lime-stabilized about 328,000 SY under the building pad, pavements, rail spur and laydown yards using about 10,300 tons of lime, placed about 135,000 tons of aggregate base and surface, and installed storm, sanitary and fire-water pipe including about 1,090 LF of 96" RCP, 124 storm structures, 23 hydrants and 26 PIVs.
- 80 acres cleared
- ~475,000 CY mass cut/fill
- ~198,000 CY structural & deep pit excavation (tunnels, mixing, cooling water, carbon unloading pits)
- ~31,000 CY topsoil stripped/respread
- ~328,000 SY lime stabilization (pad 16" @ 5%, pavements & rail 12" @ 4%, laydown 12" @ 3%) using ~10,300 tons of lime
- ~135,000 tons aggregate base & surface
- ~14,800 LF storm sewer including ~1,090 LF of 96" RCP
- 124 storm structures
- ~12,000 LF drain tile
- ~6,600 LF sanitary with 24 manholes
- ~7,800 LF DIP fire/water main
- 23 hydrants
- 26 PIVs
- Hydro-ex locating
- Full SWPPP
Related services
- Site Utilities
- Earthwork & Site Grading
- Water & Sewer
- Soil Stabilization
- Industrial & Mission Critical Sitework
- Hydrovac Excavation
- Site Demolition
What each service covered
Earthwork & Site Grading
Commercial excavation and heavy civil earthmoving for site development, roadways, and industrial pads throughout the St. Louis region.
Water & Sewer Infrastructure
Underground utility construction — water lines, sanitary sewer, storm sewer, and manholes for commercial and industrial site work.
Soil Stabilization
Lime and cement stabilization, full-depth reclamation, and subgrade improvement for asphalt contractors and site work in St. Louis.
Industrial & Mission Critical Sitework
Heavy civil sitework for industrial plants, distribution centers, and mission-critical facilities where schedule and subgrade matter.
Hydrovac & Specialty Services
Non-destructive excavation, bio pond and detention basin repair, and storm pipe cleaning.
Site Demolition
Structural and site-specific demolition with full waste management and recycling.
Other industrial projects
O'Fallon, MO
Curb removal, yard grading, crushed limestone surface, concrete approach, storm and erosion control
View project →St. Louis, MO
15" sanitary replacement, lateral repair, concrete street repair, traffic control
View project →