Project summary
For a build-to-rent single-family community in Wentzville, St. Charles County, Kuesel installed about 1,700 LF of 12" PVC sanitary main, upsized from the original 10" design.
The work included 20 LF of 12" DIP where required, 28 service wyes, 22 A-Lok/Z-Lok connections, an inside drop and testing. A 526 LF segment was lowered 2 feet and converted to C900.
| Location | Wentzville, MO |
|---|---|
| Market | Residential Development |
| Scope | 12" PVC sanitary main (upsized), DIP, wyes, drop, lowered segment converted to C900, testing |
Challenge → approach
Partway through, the design changed: the main was upsized from 10" to 12", and a 526 LF segment had a grade conflict. Kuesel lowered that segment 2 feet and converted it to C900 so the line could carry on at the new grade.
Scope delivered
- 1,760 LF 12" PVC sanitary main (upsized from 10")
- 20 LF 12" DIP
- 28 wyes
- 22 A-Lok/Z-Lok connections
- Inside drop
- Lowered 526 LF of sanitary 2 ft and converted to C900
- Testing
Key quantities
- 1,760 LF 12" PVC sanitary
- 28 wyes
- 22 manhole connections
- 526 LF lowered and converted to C900
Services used
Invite Kuesel to bidScope on this job
What each service covered
Water & Sewer Infrastructure
Underground utility construction — water lines, sanitary sewer, storm sewer, and manholes for commercial and industrial site work.
Related Resources
All resources →Read before you build.
GuideStormwater and Detention: What St. Louis-Area Developers Should Plan ForWho reviews stormwater where, detention and bioretention options, and land disturbance permits.Read GuideWhat Drives Site Development Cost in St. LouisThe conditions and decisions that move a sitework budget, and when you can still change them.Read