Project Overview

Client: ARCO National
Location: Fayetteville, North Carolina

DISTRIBUTION HUB

  • 627,000 Square Foot Distribution Warehouse 

  • 310,400 cubic yards of on-site cut & fill.
  • Construction of a 10 acre storm water detention basin.  Installed an HDPE liner for the storm water basin sediment trap.
  • 108,000 square yards of portland cement soil stabilization for asphalt pavement sub-base.
  • 26,000 tons of aggregate base for concrete pavement.
  • Forced evacuation of construction site in September 2018 due to Hurricane Florence.
  • Construction resumed in October 2018 and project was completed in June 2019